This excerpt is from a report that is available to subscribers of Stratas Advisors’ North America and North American Shale services.

Natural Gas Pipeline Infrastructure Updates

We had just one update regarding natural gas pipeline infrastructure in the Eagle Ford region.

Gulf South Pipeline Co. LP announced that it is replacing its existing natural gas pipeline that currently serves its Enstor Katy Storage Facility in Fort Bend County, Texas. The company plans to begin construction of the Katy Lateral Project by April 2017. Completion date is Oct. 1, 2017.

Projected Natural Gas Processing Capacity in the Eagle Ford

We had one new project update in our natural gas processing coverage of the Eagle Ford region.

Opero Energy has announced plans for its South Texas plant. The plant will process 200 MMcf/d of natural gas and produce Y-grade (mixed NGL) liquids at a facility in South Texas. Opero expects this project to be complete sometime during first-quarter 2017.