The Federal Energy Regulatory Commission (FERC) voted Feb. 15 to extend the completion deadline of Tellurian’s Driftwood project to April 2029.
Near Lake Charles, Louisiana, the Driftwood project has already received permitting permission from the U.S. Department of Energy, meaning the facility is not subject to the pause the Biden administration placed on new LNG projects in January. The project includes a pipeline and an LNG export terminal that will have a capacity of about 27.6 MMmt/year when completed.
According to the FERC, Tellurian applied for the extension in October 2023. In the extension application, the company stated it had worked diligently toward project completion but had been delayed by COVID-19’s effect on the supply chain. The company also said it needs time to secure customers and financing.
Tellurian now says the earliest phase 1 of the project could be completed is in late 2027.
Environmental group Sierra Club argued against the extension request, saying that Tellurian has mismanaged the project and that decision requires additional study to assess the environmental impact of the project. The FERC rejected the Sierra Club’s arguments in its decision.
Earlier in February, Houston-based Tellurian announced plans to sell its natural gas assets in the Haynesville Shale, using part of the proceeds to focus on development of the Driftwood project.
“Tellurian thanks FERC for working with our team to ensure the safe construction of Driftwood LNG. FERC has been diligent in its oversight, having visited the site 19 times already, and provided careful examination of this extension request,” said Tellurian CEO Octávio Simões. “We have invested over a billion dollars into Driftwood LNG’s development, we have our approval to export and all applicable construction permits, and we are eager to provide the world with liquefied natural gas exports.”
Recommended Reading
GeoPark, Vitol Sign Offtake Deal for Llanos 34 Block
2024-05-10 - Under the agreement, GeoPark will sell and deliver to Vitol a minimum of 20,000 bbl/d of oil from the Llanos 34 Block in Colombia, which GeoPark holds 45% working interest.
SCF Acquires Flowchem, Val-Tex and Sealweld
2024-03-04 - Flowchem, Val-Tex and Sealweld were formerly part of Entegris Inc.
Enbridge Closes First Utility Transaction with Dominion for $6.6B
2024-03-07 - Enbridge’s purchase of The East Ohio Gas Co. from Dominion is part of $14 billion in M&A the companies announced in September.
Pembina Cleared to Buy Enbridge's Pipeline, NGL JV Interests for $2.2B
2024-03-19 - Pembina Pipeline received a no-action letter from the Canadian Competition Bureau, meaning that the government will not challenge the company’s acquisition of Enbridge’s interest in a joint venture with the Alliance Pipeline and Aux Sable NGL fractionation facilities.
Global Partners Buys Four Liquid Energy Terminals from Gulf Oil
2024-04-10 - Global Partners initially set out to buy five terminals from Gulf Oil but the purchase of a terminal in Portland was abandoned after antitrust concerns were raised by the FTC and the Maine attorney general.