Aker BP received a go-ahead to start-up production at its Hanz accumulation as a subsea tieback to the Ivar Aasen Field in the North Sea, the Norwegian Offshore Directorate (NOD) announced Feb. 27.
Hanz was proven in 1997 and is included in the 2013 plan for development and operation for the Ivar Aasen Field.
The project in 380 ft water depth is reusing the subsea installations on the Jette Field, which was shut down in 2016.
In a press release, NOD’s Tomas Mørch, assistant director of license management, called the use of existing infrastructure and an alternative method for pressure support a good use of resources.
Development costs for Hanz were about $400 million, and the project targets recovering about 20 MMboe.
Aker BP expects to begin production during the first quarter of 2024.
Aker BP operates PL028 B with 35% interest on behalf of partners Equinor with 50% and Sval Energi with 15%.
Recommended Reading
Global Oil Demand to Grow by 1.9 MMbbl/d in 2024, Says Wood Mac
2024-02-29 - Oil prices have found support this year from rising geopolitical tensions including attacks by the Iran-aligned Houthi group on Red Sea shipping.
Russia Orders Companies to Cut Oil Output to Meet OPEC+ Target
2024-03-25 - Russia plans to gradually ease the export cuts and focus on only reducing output.
Oil Rises After OPEC+ Extends Output Cuts
2024-03-04 - Rising geopolitical tensions due to the Israel-Hamas conflict and Houthi attacks on Red Sea shipping have supported oil prices in 2024, although concern about economic growth has weighed.
What's Affecting Oil Prices This Week? (April 8, 2024)
2024-04-08 - Stratas Advisors says geopolitics are providing a boost for oil prices as conflicts escalate–and while crude oil and oil products continue to flow, the possibility of disruption is increasing.
US Leads Global Oil Production for Sixth Straight Year-EIA
2024-03-11 - The Energy Information Administration says it is unlikely that the record will be broken by another country in the near term.