First oil flowed at phase two of Oil and Natural Gas Corp. Ltd.’s (ONGC) deepwater KG-DWN-98/2 Block in the Bay of Bengal on Jan. 7, the Indian operator announced on Jan. 8.
The waxy crude of the M Field—part of Phase 2—required the use of pipe in pipe technology, which had not been previously used offshore India, according to ONGC.
ONGC estimates the 98/2 project in the Krishna Godavari Basin offshore East India will increase the company’s oil production by 11% and gas production by 15%.
Phase 1 began production in March 2020, with gas flowing from the block’s U Field.
ONCG said the final phase of the 98/2 project in 4,265 ft water depth is on track for the remaining oil and gas fields to begin production by mid-2024. In November, McDermott announced winning a contract to transport and install a central processing platform and living quarters for the 98/2 project.
Peak production is expected at 45,000 bbl/d and 10 MMcm/d.
Recommended Reading
Keeping it Simple: Antero Stays on Profitable Course in 1Q
2024-04-26 - Bucking trend, Antero Resources posted a slight increase in natural gas production as other companies curtailed production.
Oil and Gas Chain Reaction: E&P M&A Begets OFS Consolidation
2024-04-26 - Record-breaking E&P consolidation is rippling into oilfield services, with much more M&A on the way.
Exxon Mobil, Chevron See Profits Fall in 1Q Earnings
2024-04-26 - Chevron and Exxon Mobil are feeling the pinch of weak energy prices, particularly natural gas, and fuels margins that have cooled in the last year.
Marathon Oil Declares 1Q Dividend
2024-04-26 - Marathon Oil’s first quarter 2024 dividend is payable on June 10.
Talos Energy Expands Leadership Team After $1.29B QuarterNorth Deal
2024-04-25 - Talos Energy President and CEO Tim Duncan said the company has expanded its leadership team as the company integrates its QuarterNorth Energy acquisition.