Neptune Energy has successfully installed subsea oil and gas production flowlines and gas lift flowlines for its Duva & Gjøa P1 developments in the Norwegian sector of the North Sea, the company said on July 23.
Neptune and its partners accelerated key elements of the development schedule of the subsea tiebacks, which will connect two templates to the nearby Neptune-operated Gjøa platform, with Gjøa P1 in particular on track to achieve first oil two months ahead of the original plan. Parallel works have been conducted where possible across the drilling, engineering, fabrication and installation disciplines.
The milestones were reached just one year after the development plans for the Duva (PL636) and Gjøa P1 (PL153) projects were approved by the Norwegian authorities.
“Developing these two live projects in parallel provides greater flexibility and allows Neptune and its partners to increase efficiency and reduce costs. We have taken a campaign approach in our use of vessels and common equipment, achieving positive synergies through joint mobilization and focusing on collaboration between project teams for Neptune and our key contractors and partners,” Crawford Brown, Neptune’s head of the subsea Gjøa project, said.
Final fabrication of the tie-in spools for the development projects is ongoing at TechnipFMC’s spoolbase in Evanton, U.K. The manufacture of both Duva and Gjøa P1 subsea manifolds is nearing completion, and full system integration testing is underway.
The subsea manifolds are scheduled for installation later this year, followed by the associated tie-in operations. Development drilling on both Gjøa P1 and Duva will continue up to the end of February next year, while key topside work on the Gjøa platform will be carried out consecutively.
Neptune anticipates first production from Gjøa P1 later this year, with first production from Duva anticipated in the third quarter of 2021.
Recommended Reading
Baker Hughes Awarded Saudi Pipeline Technology Contract
2024-04-23 - Baker Hughes will supply centrifugal compressors for Saudi Arabia’s new pipeline system, which aims to increase gas distribution across the kingdom and reduce carbon emissions
BP Restructures, Reduces Executive Team to 10
2024-04-18 - BP said the organizational changes will reduce duplication and reporting line complexity.
OFS Sector Loses Jobs, but Trade Org Says Growth Potential Remains
2024-05-08 - According to analysis by the Energy Workforce & Technology Council, the OFS job market may still have potential for growth despite a slight decrease in the sector in April.
Dividends Declared in the Week of May 6
2024-05-10 - Here is a selection of upstream, midstream and service and supply companies’ dividends declared in the past week.
Kimmeridge Fast Forwards on SilverBow with Takeover Bid
2024-03-13 - Investment firm Kimmeridge Energy Management, which first asked for additional SilverBow Resources board seats, has followed up with a buyout offer. A deal would make a nearly 1 Bcfe/d Eagle Ford pureplay.