Date | Kansas | Oklahoma | TX Dist. 7B | TX Dist. 7C | TX Dist. 8 | TX Dist. 8A | TX Dist. 9 | TX Dist. 10 |
SEPT. 10 | 0 | 32 | 3 | 19 | 149 | 12 | 0 | 3 |
SEPT. 17 | 0 | 35 | 3 | 20 | 140 | 14 | 0 | 3 |
SEPT. 24 | 0 | 39 | 3 | 19 | 143 | 12 | 0 | 3 |
OCT. 1 | 0 | 40 | 3 | 21 | 142 | 13 | 0 | 3 |
OCT. 8 | 0 | 41 | 3 | 21 | 146 | 12 | 0 | 3 |
OCT. 15 | 0 | 43 | 4 | 22 | 148 | 11 | 0 | 3 |
OCT. 22 | 0 | 43 | 4 | 25 | 144 | 11 | 0 | 3 |
OCT. 29 | 0 | 43 | 4 | 25 | 144 | 11 | 0 | 3 |
NOV. 5 | 0 | 44 | 4 | 23 | 149 | 12 | 0 | 3 |
NOV. 12 | 0 | 44 | 4 | 23 | 152 | 15 | 0 | 3 |
NOV. 19 | 0 | 44 | 4 | 23 | 156 | 15 | 0 | 3 |
NOV. 26 | 0 | 44 | 4 | 23 | 158 | 15 | 0 | 3 |
DEC. 3 | 0 | 44 | 4 | 23 | 157 | 14 | 0 | 3 |
DEC. 10 | 0 | 46 | 5 | 21 | 158 | 14 | 0 | 3 |
DEC. 17 | 0 | 48 | 5 | 21 | 162 | 13 | 0 | 1 |
DEC. 24 | 0 | 48 | 5 | 22 | 166 | 10 | 0 | 3 |
DEC. 31 | 0 | 49 | 5 | 22 | 164 | 10 | 0 | 3 |
JAN. 7 | 0 | 49 | 5 | 22 | 162 | 10 | 0 | 3 |
Created By: Larry Prado - Activity Editor
Source: Baker Hughes
Recommended Reading
Waha NatGas Prices Go Negative
2024-03-14 - An Enterprise Partners executive said conditions make for a strong LNG export market at an industry lunch on March 14.
Summit Midstream Launches Double E Pipeline Open Season
2024-04-02 - The Double E pipeline is set to deliver gas to the Waha Hub before the Matterhorn Express pipeline provides sorely needed takeaway capacity, an analyst said.
For Sale? Trans Mountain Pipeline Tentatively on the Market
2024-04-22 - Politics and tariffs may delay ownership transfer of the Trans Mountain Pipeline, which the Canadian government spent CA$34 billion to build.
Pembina Pipeline Enters Ethane-Supply Agreement, Slow Walks LNG Project
2024-02-26 - Canadian midstream company Pembina Pipeline also said it would hold off on new LNG terminal decision in a fourth quarter earnings call.
EQT CEO: Biden's LNG Pause Mirrors Midstream ‘Playbook’ of Delay, Doubt
2024-02-06 - At a Congressional hearing, EQT CEO Toby Rice blasted the Biden administration and said the same tactics used to stifle pipeline construction—by introducing delays and uncertainty—appear to be behind President Joe Biden’s pause on LNG terminal permitting.