Aker BP received a go-ahead to start-up production at its Hanz accumulation as a subsea tieback to the Ivar Aasen Field in the North Sea, the Norwegian Offshore Directorate (NOD) announced Feb. 27.
Hanz was proven in 1997 and is included in the 2013 plan for development and operation for the Ivar Aasen Field.
The project in 380 ft water depth is reusing the subsea installations on the Jette Field, which was shut down in 2016.
In a press release, NOD’s Tomas Mørch, assistant director of license management, called the use of existing infrastructure and an alternative method for pressure support a good use of resources.
Development costs for Hanz were about $400 million, and the project targets recovering about 20 MMboe.
Aker BP expects to begin production during the first quarter of 2024.
Aker BP operates PL028 B with 35% interest on behalf of partners Equinor with 50% and Sval Energi with 15%.
Recommended Reading
CERAWeek: Tecpetrol CEO Touts Argentina Conventional, Unconventional Potential
2024-03-28 - Tecpetrol CEO Ricardo Markous touted Argentina’s conventional and unconventional potential saying the country’s oil production would nearly double by 2030 while LNG exports would likely evolve over three phases.
Woodside Brings in the Know-how
2024-04-01 - Woodside Energy Group CEO Meg O’Neill is relying on technical sophistication to guide the Australian giant as it takes on three challenging projects in the U.S. Gulf of Mexico.
Wirth: Chevron Won’t Put ‘New Capital into Venezuela’
2024-05-01 - California-based Chevron Corp. doesn’t plan on allocating more capex into its operations in Venezuela even though it still has U.S. approval to operate there, despite Washington sanctions.
Repsol Plans to Double Oil Production in Venezuela
2024-05-01 - Spain’s Repsol plans to double its oil production in Venezuela and continue with its diluent swap agreements with the OPEC country as approved by the U.S. government.
What's Affecting Oil Prices This Week? (May 13, 2024)
2024-05-13 - For 2024, increasing supply will be more challenging unless U.S. producers start ramping up their capex and drilling programs beyond their current plans.