Since April 10, Freeport LNG has been operating at a fraction of its capacity, hitting natural gas prices in an already weak market.
Reuters reported April 15 that the natural gas liquefaction facility was operating at 5% of capacity at 125 MMcf/d. Freeport LNG takes in about 2.2 Bcf/d of natural gas when at normal operational levels.
The company has been quiet on the most recent shutdown. A spokeswoman told Hart Energy on April 16 that it has no new information since its last update in March.
The drop in gas uptake follows a series of issues with all three of the company’s on-site trains going as far back as April 2023.
This year, a January cold snap damaged the electrical engines in Train 3, causing a shutdown for repairs. The incident caused Freeport LNG to schedule follow-up repairs on its other two trains to avoid a repeat of the incident. Company officials announced that the Train 2 liquefaction unit had been shut down on March 20, and expected Train 1 to be shut down shortly after.
Each Freeport train can turn about 700 MMcf/d of gas into LNG.
The company had planned to use the repair time to speed up a debottlenecking project. Bloomberg reported Freeport LNG was working on a debottlenecking project that would add additional compressor capacity for all three of the trains on site.
The debottlenecking work was scheduled for completion in June and designed to increase the plant’s production capacity from 15 million tonnes per year (mtpy) to 16.5 mtpy.
The Train 3 liquefaction unit experienced a trip on April 10, according to a report Freeport LNG filed with Texas regulators. Prior to the most recent shut down, Freeport LNG had said that it expected to return to full capacity in May.
The shutdown comes at a time when natural gas producers are already dealing with an oversupply that has kept the price of Henry Hub futures below $2 per MMBtu since early February. After briefly reaching $1.93/MMBtu on April 10, the price slipped below $1.66/MMBtu on April 16.
Natural gas demand from U.S. LNG liquification facilities is around 12.6 Bcf/d, according to equity research firm TPH&CO. Venture Global’s Calcasieu Pass also fell to about 1 Bcf/d of feed gas demand during the week.
Recommended Reading
US Asks Venture Global LNG to Justify Filing of Confidential Documents
2024-03-13 - The FERC request comes days after Venture Global LNG customers had challenged the company's request for a one-year extension of its startup and urged the regulator to make Venture Global release the confidential commissioning documents.
Venture Global Gets FERC Nod to Process Gas for LNG
2024-04-23 - Venture Global’s massive export terminal will change natural gas flows across the Gulf of Mexico but its Plaquemines LNG export terminal may still be years away from delivering LNG to long-term customers.
Williams Cos. Blasts Energy Transfer’s FERC Filing
2024-05-15 - In response to Energy Transfer, Williams says the rival’s action is “lawfare” to delay the company’s Louisiana Energy Gateway project.
Watson: Implications of LNG Pause
2024-03-07 - Critical questions remain for LNG on the heels of the Biden administration's pause on LNG export permits to non-Free Trade Agreement countries.
Despite LNG Permitting Risks, Cheniere Expansions Continue
2024-02-28 - U.S.-based Cheniere Energy expects the U.S. market, which exported 86 million tonnes per annum (mtpa) of LNG in 2023, will be the first to surpass the 200 mtpa mark—even taking into account a recent pause on approvals related to new U.S. LNG projects.