The U.S. Federal Energy Regulatory Commission (FERC) on Oct. 7 approved the request of a unit of Glenfarne Group LLC to give it five more years, until April 2026, to complete the Magnolia LNG export plant in Louisiana.
FERC approved construction of Magnolia and related pipeline expansions by a unit of Kinder Morgan Inc. in April 2016.
That approval required the companies to complete the project within five years, by April 2021.
Glenfarne, which acquired Magnolia from LNG Ltd of Australia in May 2020, said “unforeseeable developments in the global LNG market have affected Magnolia’s ability to enter into long-term LNG offtake contracts ... critical to securing project financing and achieving (final investment decision),” referring to purchase agreements for gas.
Those “unforeseeable developments” included global energy demand destruction from government lockdowns to stop the spread of the coronavirus and disruptions caused by the U.S.-China trade war.
Glenfarne has said it expects to decide late next year whether to build the Magnolia plant and the Texas LNG facility it is developing in that state. If the company decides to build the projects, they could enter service around 2025.
Several developers have put off decisions to build LNG projects in North America over the past year due to uncertainty about demand as the pandemic and other factors have cut energy consumption.
Even before the pandemic, gas prices were already trading at their lowest levels in years, making customers hesitant to sign long-term deals needed to finance multi-billion-dollar LNG projects because the world was already awash in gas after a record number of export plants entered service in 2019.
Magnolia is designed to produce 8.8 million tonnes per annum of LNG, or 1.2 billion cubic feet per day of natural gas. One billion cubic feet is enough gas to supply about 5 million U.S. homes for a day.
Recommended Reading
Bobby Tudor on Capital Access and Oil, Gas Participation in the Energy Transition
2024-04-05 - Bobby Tudor, the founder and CEO of Artemis Energy Partners, says while public companies are generating cash, private equity firms in the upstream business are facing more difficulties raising new funds, in this Hart Energy Exclusive interview.
GE Vernova Completes Spin-Off from GE
2024-04-04 - GE Vernova, an energy transition company, began trading as an independent company on the New York Stock Exchange this week.
Viper Energy Announces Pricing of Diamondback’s Secondary Common Stock Offering
2024-03-06 - Viper Energy will not receive any of the gross proceeds from Diamondback’s secondary offering of its Class A common stock.
First Solar’s 14 GW of Operational Capacity to Support 30,000 Jobs by 2026
2024-02-26 - First Solar commissioned a study to analyze the economic impact of its vertically integrated solar manufacturing value chain.
SunPower Begins Search for New CEO
2024-02-27 - Former CEO Peter Faricy departed SunPower Corp. on Feb. 26, according to the company.